A , b, c along complete a work in 15 , 20 and 30 days. all together start the work, after 4 days, a left the work, next after 4 days b left the work. rest work done by

c. they got rs. 4500 for whole work. find the share of b

Answers

Answered by jjp2468
0
share will be 900 for b