A, b, c and d can do a piece of work in 40 days. if a and b can do it together in 100 days, and c alone in 120 days, find the time in which d alone can do it.
Answers
Answered by
0
Consider the time required by A to finish the work be a days, similarly for others B in b days, C in c days, D in d days.
Work done by each in one day
A= 1/a
B= 1/b
C= 1/c
D = 1/d
If they all work together, the amount of work done in one day is 1/40,
if A and B work together then 1/100,
if C alone then 1/120
thus: 1/a + 1/b +1/c 1/d = 1/40
1/a +1/b =1/100
1/c = 1/120
By substituting the values you can calculate for D
Work done by each in one day
A= 1/a
B= 1/b
C= 1/c
D = 1/d
If they all work together, the amount of work done in one day is 1/40,
if A and B work together then 1/100,
if C alone then 1/120
thus: 1/a + 1/b +1/c 1/d = 1/40
1/a +1/b =1/100
1/c = 1/120
By substituting the values you can calculate for D
Answered by
0
The time taken by d to complete the work alone is 150 days.
Given,
a,b,c, and d do a piece of work in 40 days.
a and b together complete work in 100 days.
c alone completed the work in 120 days.
To Find,
the time in which d alone can complete the work.
Solution,
a+b+c+d=40 days
a+b=100days
c=120
let's take the L.C.M of the 40,100 and 120
LCM of 100, 120 and 40 = 600
so,
a+b+c+d== 15 unit / day.
a+b== 6 unit / day.
c== 5 unit / day.
then,
a+b+c+d= 15 unit / day
on putting values of a+b and c in the above
6+5+d=15
d= 15-11
d=4 unit / day.
so,
d=
d= 150 days.
The time taken by d to complete the work alone is 150 days.
#SPJ2
Similar questions