Math, asked by psunita1090, 5 months ago

A B C can complete a work in 24days,15 days and 10 days respectively.If A and B start the work together and worked for 3 days,then how many days C alone will take to finish the work​

Answers

Answered by saivaruntej11
1

Answer:

4/13

Step-by-step explanation:

(A+B+C)'s one day's work= 13/60

Only C = 4/13

Answered by sanjuashmita
1

Answer:

click on the attachment

Step-by-step explanation:

Please select my answer as soon as possible as BRAINLIST

Attachments:
Similar questions