A B C can complete a work in 24days,15 days and 10 days respectively.If A and B start the work together and worked for 3 days,then how many days C alone will take to finish the work
Answers
Answered by
1
Answer:
4/13
Step-by-step explanation:
(A+B+C)'s one day's work= 13/60
Only C = 4/13
Answered by
1
Answer:
click on the attachment
Step-by-step explanation:
Please select my answer as soon as possible as BRAINLIST