Math, asked by nishthajain15, 7 months ago

a b c can do a piece of work in 10 days A alone can do it in 40 days B alone can do it 30 days in how many days will c alone can complete the work??​

Answers

Answered by sarina7982
0
So that means c or a is the answer there
Answered by MyOwnWorstCritic
2

Answer:

Step-by-step explanation:

A, B and C can do piece of work in 10 days

so they can do 1/10 part of work in a day

A alone can do same work in 40 days

so A can do 1/40 part of work in a day

B alone can do it in 30 days

so B can do 1/30 part of work in a day

let the days taken by C be x

1/10=1/40+1/30+1/x

1/10=7/120+1/x

1/10-7/120=1/x

12-7/120=1/x

5/120=1/x

1/24=1/x

Therefore, C can do 1/24 in a day .

So, C can do whole piece of work in 24 days.

Hope it helps!