A,B,C can do a piece of work in 12,15and 20days respectively. How long will they take to do it working together.

Answers

Answered by BalaSelvam6698
2

Answer:

5 days.

Explanation:

A=1/12 work in 1 day.

B=1/15 work in 1 day.

C=1/20 work in 1 day.

Therefore,

=(1/12)+(1/15)+(1/20)

=(5+4+3)/60 [ LCM of 12,15,20 is 60 ]

=12/60

= 5 days.