A ,b ,c can do a piece of work in 6, 8, 12 hours respectively they started the work together and after 1 hours b left the work in how much time will be remaining work be completed by a and c​

Answers

Answered by Kowshik1178
2

Answer:

Here is the answer

The image is some

blur don't mind

Sorry,

Attachments:
Answered by mohmmadkhizar58
1

Answer:

Correct option is

A

2

Work done by B & C in 2 days = 2×{81+121}=125th part of the work

Remaining work = (1−125)th=127th part

A and B's one day work = (61+81)th=(247)th part

So 247th part of work is completed in 1 day 

∴ 127th part of work will be completed in 

= 7/241×127=724×127=2 days