Math, asked by ashish937, 1 year ago

A,B,C can do a piece of workin 10,12and 25 days respectively.After 3days ,B left the work. In how many days,the remaining work will be completed by both A and C together?​

Attachments:

Answers

Answered by gps69
0

remaining work will be completed by both "A"and "B" together in 44 days