A, B, C can do a work in 6,8,12 days respectively. B and C work together for 2 days, Then A takes C's place. How long will it take to finish the work
Answers
Answered by
0
2(B+C)= 2(1/8+1/12)
2×5/24=5/12
last work = 1-5/12
7/12
A+C= 1/6+1/12
=3/12=4
7/12×4
=7/3
finish work is 2+7/3=13/3 days