Math, asked by aryansingh304571, 11 months ago

A,B,C can do apeace of work in 15,12,20 respectively. They started the work together , but C left after 2 days , In how many days the remaining work be completed by A and B.

Answers

Answered by Pruthil123
2

On the 1st day of the work,

Total work done by A, B and C =

( Take the LCM of 15, 12 and 20 )

L.C.M = 60

Now,

We get,

=

=

Therefore,

On the 2nd day of work,

A, B and C  would have done work.

For A and B ( on the first day of work ) :

=

( Take L.C.M of 12 and 15 )

=

Now,

It remains for of the work.

= ÷ 

= × 

= 4

Answer : 4 days will be the remaining work to be done by A and B