Math, asked by adarshhuih, 10 months ago

A b c can finish task in 42 days 84 days 28 days.a started work b joined him after 3 days if c joined after 5 days from.beginning for bpw many days a work

Answers

Answered by TooFree
5

Question (Corrected):

A B and C can finish task in 42 days, 84 days and 28 days respectively. A started work. B joined him after 3 days. C joined after 5 days from.beginning. How many days did A worked for?

Given:

A can finish the work in 42 days.

B can finish the work in 84 days.

C can finish the work in 28 days.

A started working.

B joined in 3 days later.

C joined in 5 days later.

To Find:

Number of days A worked.

Solution:

A can finish the work in 42 days.

1 day = 1/42 of the work

B can finish the work in 84 days.

1 day = 1/84 of the work

C can finish the work in 28 days.

1 day = 1/28 of the work

Find the amount of work done in the first 3 days:

Work done  (by A alone) = 3 x 1/42

Work done (by A alone) = 1/14

Find the amount of work done in the next 2 days:

Work done (by A and B) = 2 x ( 1/42 + 1/84)

Work done (by A and B) = 1/14

Find the work completed in the first 5 days:

Work done = 1/14 + 1/14

Work done = 1/7

Find the amount of work undone:

Work undone = 1 - 1/7

Work undone = 6/7

Find the amount of work that the 3 of them can complete in a day:

Work done in a day (By A, B and C) = 1/42 + 1/84 + 1/28

Work done in a day (By A, B and C) = 1/14

Find the number of days needed:

Number of days needed = 6/7 ÷ 1/14

Number of days needed = 12

Find the number of days that A needs to work:

Number of days worked = 5 + 12

Number of days worked = 17

Answer: A worked for 17 days

Answered by shraddhadhiraj84
1

Answer:

A worked for 17 days......