A ,B,C together can complete a work in 40 days.A+B can complete this work in 33.33% lesser time than C.While B can complete the same work in 33.33% more time than A+C .Find time taken by B+C to complete the work
Answers
JobA can complete the work alone in 36 days.
B is 33.33% more efficient than A
B can finish the work alone in 27 days.
Both can do 1/36 + 1/27= 7/108 of the work in 2 days.
So when they do on alternate days in 30 days they will do 15(7/108) = 105/108 of the work and 3/108 = 1/36 is still left over. And since A started the work and his capacity is 1/36 of the work, he will finish the remaining work in 1 day.
Hence the total number of days taken by A and B to do the work when they do on alternate days with A starting the work is 30+1 =31 days.
Step-by-step explanation:
JobA can complete the work alone in 36 days.
B is 33.33% more efficient than A
B can finish the work alone in 27 days.
Both can do 1/36 + 1/27= 7/108 of the work in 2 days.
So when they do on alternate days in 30 days they will do 15(7/108) = 105/108 of the work and 3/108 = 1/36 is still left over. And since A started the work and his capacity is 1/36 of the work, he will finish the remaining work in 1 day.
Hence the total number of days taken by A and B to do the work when they do on alternate days with A starting the work is 30+1 =31 days.
A and B together can complete a piece of work in 12 days, B and C together can complete a piece of work in 16 days, A and C together can complete a piece of work in 24 days. Find the number of days in which A, B and C together can complete the work.