Math, asked by harshitnag4275, 1 year ago

A+b can complete a work in 30days they start work together and after 23 daysvb left the work and whole work complete in 33 days

Answers

Answered by gowtham16
0
a does 7/300 work in 1day
b does 1/100 work in 1day