A+B can do a work in 10 days , B+C can can do it in 12 days , A+C can do it in 15 days. All 3 work for 6 days and A leaves. In how many days will be B+C finish it working together?Solve it step by step
Answers
Answered by
4
A+B can do a work in 10 days
B+C can can do it in 12 days
A+C can do it in 15 days
Take the LCM of 10, 12 ,15 which is 60.
So , the total unit of work is 60 units
A+B can do 60 / 10 = 6 units per day ---- eq. 1
B+C can do 60 / 12 = 5 units per day ---- eq. 2
A+C can do 60 / 15 = 4 units per day ---- eq. 3
Add all the eq.s
A+B+B+C+A+C = 6 + 5 + 4
2A + 2B + 2C = 15
2 ( A + B + C ) = 15
A + B + C = 7.5 units
Now all 3 work for 6 days so , 7.5 × 6 = 45 units
Now remaining = 60 - 45 = 15 units
Now A leaves
B + C = 5 units per day
So , 15 / 5 = 3 days
So, B + C finishes work in 3 days
Total work completed in 6 days + 3 days.
So the correct answer is 3 days.
Hope it helps....