A, B तथा C एक काम को क्रमश: 10, 12 और 15 दिनों में समाप्त कर सकते हैं। यदि 'B' 2 दिन काम करके छोड़ दे, तो शेष काम A और C कितने दिनों में समाप्त करेंगे।
Answers
Given
A can complete the work in 10 days.
B can complete the work in 12 days.
C can complete the work in 15 days.
B works only 2 days .
To find :-
In how many days the remaining work will be completed after leaving B .
Solution :-
The total amount of work is 1.
A can do work in 1 day = 1/10
B can do work in 1 day = 1/12
C can do work in 1 day = 1/15
→ Work done by B in 2 days = (1/12).2
→ So B did 1/6 th part of work .
Work left for A and C = 1 - 1/6
→ 5/6 th part of work.
Work done by A and C together in starting 2 days = 2/10 + 2/15 = 1/3rd part.
Now After 2 days remaining work= 5/6 - 1/3
→ 1/2 nd part of work is left for A and C.
A+C. = 1/10 + 1/15 = 1/6
They both can do 1/6 th part of work in a day .
So 1/2 part of work will complete in = (1/2)/(1/6) days
→ 3 days .
So The remaining work will be completed by A and C in 3 days
__________________________
- A could complete a work in 10 days
- B could complete a work in 12 days
- C could complete a work in 15 days
- B works only 2 days.
__________________________
- In how many days the remaining work would be done as well as B have lefted.
__________________________
Let the total amount of work be 1 unit
Then,
A = 1/10 of a unit
B = 1/12 of a unit
C = 1/15 of a unit
↪work by B in 2 days = 1/12th × 2
↪work done be B = 1/6 th unit
_________________________
Work left for A & C = 1-(1/6) or 5/6 of the work
Then,
Work done by A & C in first 2 days = (2/10 +2/15)of the unit or ⅓ of the work
_________________________
Now, left work after these two days,
↪Left work = 5/6 - 1/3
↪Left work = ½ of a unit
They both can do 1/6 of a unit in a day
so,
↪½ of the work would be completed in = (½)÷(1/6)
↪½ of the work would be completed in = 3 Days
_________________________
Hence,