A,Band C can do a piece of work in 15,12 and 20 days,respectively.they started the work together,but C left after 2 days.in how many days will the remaining work be completed by A and B
Answers
Answered by
9
Answer.
A and B will take another 4 days to complete the remaining work
A and B will take another 4 days to complete the remaining work
Attachments:
princejha74:
but i need the solution in detail...
Answered by
1
A and B will do the work in another 4 days