A, Band C can do a piece of work in days, 30 days and 40 days respectively. They b the work together but C left 4 days before the completion of the work. In how many was the work completed?
Answers
Answered by
1
Step-by-step explanation:
one days work of each of A,B and C is
1/24 =5/120 ,1/30=4/120 and 1/40=3/120 respectively
so that their one days work when all three work together is
(5/120)+(4/120)+(3/120)=12/120 =1/10 th part of the whole work
so they all together can complete the work in 120/12 =10 days
C left 4 days before means 4 x 1/10 = 4/10 part of work is left
A and B s one days work is 5/120 + 4/120 =9/120 th part
so they can complete whole the work in 120/9 days
and they can complete 4/10 th part of work in
4/10 x120/9 =16/3 days or 5+ (1/3) days
total work will be completed in 6+ 5+(1/3)=11+(1/3) days