A boundary wall of length 8 km is to be built to the north of desert island Miramar. Two workers A and B can build 50 m and 70 m per day respectively. But A takes day off after working every 3 days and B takes 2 days off after working every 4 days. In how many days the wall will be built? (A) 93 days (B) 94 days (C) 95 days (D) 96 days (E) None of These
mkrishnan:
answer is 94
Answers
Answered by
25
Hey Buddy
Here’s the answer...
_________________________
# From attachment it is clear that the same pattern of working is followed after 12 days ..
#No work is done on 12th day
=> A and B together make 120 meter a day
So ,
=> In 12 days 1010 meter wall will be constructed
=> 12 days = 1010 meter
=> 1 meter = 12 / 1010 days
We know 8 Km = 8000 m
=> 8000 m = 12 * 8000 / 1010 days
=> 8000 m = 95.04 days
=> so it will take 95 days to buit that wall
HOPE HELPED
JAI HIND
:)
Attachments:
Answered by
23
________________
________
________
_________________
step-by-step explanation:
Given,
A takes day off after working every 3 days
It means that,
A won't work on
4th, 8th, 12th, 16th.....days
Similarly,
B takes 2 days off after working every 4 days
It means that,
B won't work on
5th, 6th, 11th, 12th......days
Therefore,
we see that,
on every 12th day , no work is done,
i.e., on 12th, 24th, 36th......days
no work is done by any of A and B.
Now,
total length of wall that can be built both by A and B = (70+50) = 120m
Therefore,
in 12 days,
(50×9)+(70×8) = (450+560) = 1010 m wall is built.
now,
Using unit and proportion,
12 days = 1010 m
=> 1 m = days
length of wall required to be built = 8 km
i.e., 8000 m (°.° 1km = 1000m)
=> 8000 m = days
=> 8000 m = 95.04 days
=> 8000 m = 95 days
Hence,
it will take to build the wall.