A bridge can constructed by 1800 works in 50 days.How many more such works should be employed to complete the work in 30 days
Answers
Answered by
2
Answer:
3000 Workers are needed to complete the bridge in 30 days
Step-by-step explanation:
Here we have to do it with indirect variation
Workers needed to complete in 50 days=1800
Workers needed to comolete in 1day=1800*50 (less worker=more work on each=time increased)
Workers needed to complete in 30days =1800*50
30
=3000 workers