a builder completes and apartment by employing 490 workers in 8th month if he wishes to complete the apartment in 7 month how many more workers should be employed
Answers
Answered by
9
here you go mate. mark me as brainliest
Attachments:
Answered by
7
There are 70 more workers that should be employed.
Step-by-step explanation:
Since we have given that
Number of workers = 490
Number of months they finish their work = 8
If the number of months they should be employed for = 7
Then, we need to find the number of workers needed.
According to question, it becomes ,
More workers would be
Hence, there are 70 more workers that should be employed.
# learn more:
''A contractor employs a work for 600 men to complete a project in 8 months. He was asked to complete the work in 6 months. How many extra workers should he employ?''