Math, asked by chiranjeeviyadav, 11 months ago

A builder decided to build a farmhouse in 40 days . He employed 100 men in the beginning and 100 more after 35 days and completed the construction in stipulated time. if he had not employed the additional men, how many days behind schedule would it have been finished?

Answers

Answered by sabin67
2
i though logicaly they must take 45 daus

chiranjeeviyadav: please write the solution
chiranjeeviyadav: wrong answer
chiranjeeviyadav: correct answer is 5 days
Alishatandon99563545: Are you sure about answer .I think answer is 2.5days.
chiranjeeviyadav: solve this
Answered by Alishatandon99563545
13

In this question 200 men do the rest of work in 5days.

Therefore 100 men will do it in =5×200/100.=10 days.

It's means that they take total 45 days to complete it.

Hence 5 (45-40)additional days would be taken by 100 works to complete that work.


chiranjeeviyadav: thanks on your response