Physics, asked by rp33, 11 months ago

a bulletA bullet of mass 30g strikes a target with velocity of 90 m/s and is brought to rest after penetrating 15cm into it . Calculate work done by the bullet​

Answers

Answered by yashraj12342385
5

Explanation:

work done=change in kinetic energy

K.E=1÷2mv^2

=1÷2m×v×v×m÷m

=1÷2p^2÷m ( since,p=mv)

=p^2÷2m

p=mv

=30÷1000×90

=2.7kg.m/s

work done =p^2÷2m

=(2.7)^2÷2×0.03

=121.5j