A business plans to make 15,000 coats per annum, each taking the 1.5 direct labour hours. If the direct labour rate is $8 per hour and a pay rise of 15% is awarded halfway through the year, what is the total annual direct labour budget?

Answers

Answered by ssinghvart
7

Answer:

correct answer is 193,500

Explanation:

15,000 x 1.5 hours at $8 = $180,000 pa. The first half of the year will be $90,000 and the second half $90,000x 1.15 = $103,500. Total year = $193,500.

please follow me and make me brainlist

Answered by divyanjali714
0

Given: A business makes 15,000 coats annually. Each coat taking 1.5 labor hours. The direct labor rate is $8.

Find: Calculate the total annual direct labor budget.

Solution:

Total cost= 15,000X1.5X$8

                =$1,80,000 p.a.

First half year labor cost=$1,80,000/2

                                       = $90,000

After rising the price by 15%

Second half year labor cost=$90,000X1.15

                                             =$1,03,000

Total budget=$90,000+1,03,000

                    =$1,93,000.

Final answer: Total annual direct labor budget is $1,93,000.

#SPJ3