A can complete 2/3 part of a work in 10days. A can cimplete 1/3 part of the same work in
Answers
Answered by
0
Step-by-step explanation:
to complete 2/3part takes 10 day
then,to complete 1/3part takes (10×1/3)÷2/3=ans
Answered by
0
Answer: 5
Step-by-step explanation:
to complete 2/3part takes 10 day
then,to complete 1/3part takes (10×1/3)÷2/3= 5