Math, asked by Shreyes2274, 1 year ago

A can complete a peice of work in 10 days while b takes 15days.Together how much time will they take?

Answers

Answered by Shreya0504
0
Hey mate!!

Here's your answer

A's one day work = 1/10

B's one day work = 1/15

(A+B)'s one day work = (1/10)+(1/15) = 1/6

Therefore,
Together they can finish the work in 6 days....

Hope it helped you.....Please mark me as brainliest....