A can complete a piece of work in 10days ,b in 15 days and c in 20 days .A and c worked together for two days and then a was replaced by



b.In how many days altogether was the work completed?

Answers

Answered by daksh932
1

Step-by-step explanation:

In 8 days the work was completed

hope it's helpful for you

Mark me as Brainliest

Answered by gujjarankit
0

Answer:

whole work completed in 8 days