'A' can complete a piece of work in 12 days. 'A'
and 'B' together can complete the same piece
of work in 8 days. In how many days can 'B'
alone complete the same piece of work ?
(1) 15 days
(2) 18 days
(3) 24 days
(4) 28 days
Answers
Answered by
1
Answer:
Here's ur answer
Step-by-step explanation:
Option (3) 24 days
Answered by
18
Please see the attachment for under it.
*Answer:
A——12
B—-?
A+B——8
lcm is total work iln number of ulnits
hence LCM of (12,8)=24
One day work in units of A is 2 unit
One day work in units of B is (LCM/NO of units)
One day work in units of A+B=24/8=3
hence one day work of B is 1 unit
B can do total work in LCM/1=24
B can alone complete the same piece of work in 24 days.
Hence your third option is correct.
iii) 24 days.
Hope you like it.