Math, asked by isratferdous34, 1 year ago

A can complete a piece of work in 18 days, B in 20 days and C in 30 days, B and C together start the work and forced to leave after 2 days. The time taken by A alone to complete the remaining work is:

Answers

Answered by kritarth24
5

if any doubt free to ask.....

Attachments:

isratferdous34: thnks a lot
Answered by FelisFelis
1

It would take 15 days to complete the remaining work.

Step-by-step explanation:

Consider the provided information.

A can complete a piece of work in 18 days,

Work done by A in one day: \frac{1}{18}

B in 20 days and C in 30 days,

Work done by B in one day: \frac{1}{20}

Work done by C in one day: \frac{1}{30}

B and C together start the work and forced to leave after 2 days.

Work done by B and C in two days:

2(\frac{1}{20}+\frac{1}{30})=\frac{1}{6}

That means they completed \frac{1}{6} th part now the remaining part is:

1-\frac{1}{6}=\frac{5}{6}

Time taken by A to complete \frac{5}{6} th part:

\dfrac{\frac{5}{6} }{\frac{1}{18}}=\dfrac{5}{6} \times\dfrac{18}{1}\\ \\=5\times3\\\\=15

Hence, it would take 15 days to complete the remaining work.

#Learn more

A contractor undertook to do a certain work in 75 days and employed 60 men to do it. after 25 days he found that only one-fourth of the work was done. how many more men must be employed in order that the work may be finished in time?

brainly.in/question/4046974

Similar questions