A can complete a piece of work in 18 days, B in 20 days and C in 30 days, B and C together start the work and forced to leave after 2 days. The time taken by A alone to complete the remaining work is:
Answers
if any doubt free to ask.....
It would take 15 days to complete the remaining work.
Step-by-step explanation:
Consider the provided information.
A can complete a piece of work in 18 days,
Work done by A in one day:
B in 20 days and C in 30 days,
Work done by B in one day:
Work done by C in one day:
B and C together start the work and forced to leave after 2 days.
Work done by B and C in two days:
That means they completed th part now the remaining part is:
Time taken by A to complete th part:
Hence, it would take 15 days to complete the remaining work.
#Learn more
A contractor undertook to do a certain work in 75 days and employed 60 men to do it. after 25 days he found that only one-fourth of the work was done. how many more men must be employed in order that the work may be finished in time?
brainly.in/question/4046974