A can complete a piece of work in 36 days, B in 40 days and C in 60 days. B and C together start the work and leave the work after 4 days. Find the time taken by A to complete the remaining work?
Answers
Answer:
30 days
Step-by-step explanation:
(attachment above)
Given: A can complete a piece of work in 36 days, B in 40 days and C in 60 days. B and C together start the work and leave the work after 4 days.
To find: We have to find the time taken by A to complete the remaining work.
Solution:
A can complete a work in 36 days.
B can complete work in 40 days.
C can complete work in 60 days.
Thus total work will be an l.c.m of 36,40 and 60.
Thus total work is
Thus, the total work is 360 units.
The efficiency of A, B and C respectively 360/36, 360/40 and 360/60 means 10, 9 and 6.
In one day B and C can complete 9+6=15 unit work.
Thus in 4 days, they can compete 15×4=60 units work.
Remaining work=360-60
=300 units.
Thus A can complete the remaining work in 300/10=30 days.
Thus A can complete the remaining work in 30 days.