Math, asked by chaturvedimahendra56, 4 months ago

A can complete a piece of work on 15 days and B can complete the same work in 12 days. If

both of them work together how long will they take to finish the work?​

Answers

Answered by snehitha2
6

Answer:

The time taken by A and B to finish the work together is nearly 20/3 days.

Step-by-step explanation:

Given :

  • A can complete a piece of work on 15 days
  • B can complete the same work in 12 days.

To find :

the number of days taken by them to finish the work together.

Solution :

Let's find out how much work will be completed by A and B alone in one day.

➙ A can complete a piece of work on 15 days.

In one day, work done by A = 1/15

➙ B can complete the same work in 12 days.

In one day, work done by B = 1/12

➙ Let's assume both A and B take x days to finish the work together.

In one day, work done by A and B together = 1/x

So,

Work done by A and B together in one day = Work done by A alone in one day + Work done by B alone in one day

   \sf \dfrac{1}{x}=\dfrac{1}{15}+\dfrac{1}{12} \\\\ \sf \dfrac{1}{x}=\bigg(\dfrac{1}{15} \times \dfrac{4}{4} \bigg)+ \bigg(\dfrac{1}{12} \times \dfrac{5}{5} \bigg) \\\\ \sf  \dfrac{1}{x}=\dfrac{4}{60}+\dfrac{5}{60} \\\\ \sf  \dfrac{1}{x}=\dfrac{4+5}{60} \\\\ \sf  \dfrac{1}{x}=\dfrac{9}{60} \\\\ \sf  \dfrac{1}{x}=\dfrac{3}{20} \\\\ \sf x=\dfrac{20}{3}

 x ≈ 6.67

Therefore, The time taken by A and B to finish the work together is nearly 6.67 days.


chaturvedimahendra56: thanks didi
chaturvedimahendra56: for helping me
snehitha2: My pleasure :)
Answered by Anonymous
69

\sf{Answer}

Step-by-step-explanation

Given:-

  • A can complete work on 15 days
  • B can complete work on 12 days

To find :-

  • Work done by A& B together

Solution:-

First we will find one day work of them

Work done by A = 15days

One day work of A = \sf\dfrac{1}{15}

Work done By B = 12 days

One day work done by B = \sf\dfrac{1}{12}

Work done by A&B together in day = one day work of A + one day Work of B

So , work done by A&B together

= \sf\dfrac{1}{15}+\sf\dfrac{1}{12}

= \sf\dfrac{4+5}{60}

= \sf\dfrac{9}{60}

= \sf\dfrac{3}{20}

So, Work done by A&B together in one day = \sf\dfrac{3}{20}

___________________

So, total work done by A&B together = \sf\dfrac{20}{3}

So, total work done by A&B together =\sf\dfrac{20}{3}= 6.67 days


SREXPERIMENTKING3: hi friend
SREXPERIMENTKING3: everyone saying OK but no one subscribing please subscribe
SREXPERIMENTKING3: please subscribe my you tube channel SR EXPERIMENT KING please
SREXPERIMENTKING3: please subscribe
Similar questions