A can complete a piece of work on 15 days and B can complete the same work in 12 days. If
both of them work together how long will they take to finish the work?
Answers
Answer:
The time taken by A and B to finish the work together is nearly 20/3 days.
Step-by-step explanation:
Given :
- A can complete a piece of work on 15 days
- B can complete the same work in 12 days.
To find :
the number of days taken by them to finish the work together.
Solution :
Let's find out how much work will be completed by A and B alone in one day.
➙ A can complete a piece of work on 15 days.
In one day, work done by A = 1/15
➙ B can complete the same work in 12 days.
In one day, work done by B = 1/12
➙ Let's assume both A and B take x days to finish the work together.
In one day, work done by A and B together = 1/x
So,
Work done by A and B together in one day = Work done by A alone in one day + Work done by B alone in one day
x ≈ 6.67
Therefore, The time taken by A and B to finish the work together is nearly 6.67 days.
Step-by-step-explanation
Given:-
- A can complete work on 15 days
- B can complete work on 12 days
To find :-
- Work done by A& B together
Solution:-
First we will find one day work of them
Work done by A = 15days
One day work of A =
Work done By B = 12 days
One day work done by B =
Work done by A&B together in day = one day work of A + one day Work of B
So , work done by A&B together
= +
=
=
=
So, Work done by A&B together in one day =
___________________
So, total work done by A&B together =
So, total work done by A&B together == 6.67 days