Math, asked by eshi10, 2 months ago

A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quiets 10 days before the project is completed, in how many days will the project will be completed?​

Answers

Answered by aavishka12
1

Answer:

A can complete a project in 20 days. So, A will complete  1/20th  of the project in a day.

B can complete a project in 30 days. So, B will complete  1/30th  of the project in a day.

Let the total number of days taken to complete the project be x days.

B worked for all  x  days. However, A worked for  (x−10)  days because A quits 10 days before the project is completed.

In a day, A completes 1/20th  of the project.

Therefore, A would have completed  (x−10)th/20  of the project in (x - 10) days.

In a day, B completes 1/30th  of the project.

Therefore, B would have completed  x/30th of the project in x days.

∴(x−10)/20+x/30=1 Once we solve this equation, we get  x=18.  

It will take 18 days to complete the whole project.A can complete a project in 20 days. So, A will complete  1/20th  of the project in a day.

B can complete a project in 30 days. So, B will complete  1/30th  of the project in a day.

Let the total number of days taken to complete the project be x days.

B worked for all  x  days. However, A worked for  (x−10)  days because A quits 10 days before the project is completed.

In a day, A completes 1/20th  of the project.

Therefore, A would have completed  (x−10)th/20  of the project in (x - 10) days.

In a day, B completes 1/30th  of the project.

Therefore, B would have completed  x/30th of the project in x days.

∴(x−10)/20+x/30=1 Once we solve this equation, we get  x=18.  

It will take 18 days to complete the whole project.

Answered by aartiahl001
1

Step-by-step explanation:

A+B=30 days

A+B=20/30=2/3(since they worked together 20 days)

remaining work=1/3

A-60 days

Attachments:
Similar questions