A can complete a project in 20 days and B in 16 days. They worked together for 5 days and then
A leaves. In how many days will B finish the remaining project?
Answers
Answered by
6
Step-by-step explanation:
Given A can do the work in 20 days and B can do it 16 days.
Then work done by A in one day =
And, work by B in one day =
Then, the work done by A & B in one day =
=
A & B done 5 days together then work done in A & B in 5 days =
Then friction of work left = 1 -=
Then B can do work = = 7 days.
Hope this answer helps you out.
Answered by
5
✨ Required Answer =>
If both are working together:
1/20 + 1/30 = 1/12,
which means A and B working together will complete the project in 12 days.
So,
total of 25+2 = 27 days.
Hope it will helps ✌
Similar questions