Math, asked by tahakhan29c, 4 months ago

A can complete a project in 20 days and B in 16 days. They worked together for 5 days and then
A leaves. In how many days will B finish the remaining project?​

Answers

Answered by SHALVIAGARWAL
6

Step-by-step explanation:

Given A can do the work in 20 days and B can do it 16 days.

Then work done by A in one day =  \frac{1}{20}

And, work by B in one day =  \frac{1}{16}

Then, the work done by A & B in one day =  \frac{1}{20} +  \frac{1}{16}

=  \frac{9}{80}

A & B done 5 days together then work done in A & B in 5 days =  \frac{9}{80} \times 5

Then friction of work left = 1 - \frac{9}{16} = \frac{7}{16}

Then B can do  \frac{7}{16} work =  \frac{7}{16} \times  \frac{16}{1} = 7 days.

Hope this answer helps you out.

Answered by Anonymous
5

Required Answer =>

If both are working together:

1/20 + 1/30 = 1/12,

which means A and B working together will complete the project in 12 days.

So,

total of 25+2 = 27 days.

Hope it will helps

:)

Similar questions