A can complete a task in 15 days. B is
50% more efficient than A. Both A and B
started working together on the task and
after few days, B left task and A finished
the remaining 1/3 of the given work. For
how many days A and B worked
together?
TRRB Clerk (Pre) 2017]
(a) 3 (6) 5 (c) 4 (d) 6
(e) 2
Answers
Answered by
10
A will complete work in 15 days and its efficiency is
B's efficiency is + .
=
Hence B can complete work in 10 days.
A and B together can complete work in
=>By adding efficiencies
=> +
=>
=>taking inverse
=> 6 days
So A and B together worked for x 6
i.e 4 days
Hence correct answer is option C
Similar questions