Math, asked by Anonymous, 1 year ago

A can complete a work in 10 days , B in 12 days , and C in 15 days . All of them begin the work together , but A had to leave the work after 2 days of the start and B , 3 days before the completion of the work . How long did the work last?​

Answers

Answered by systemboss
5

Answer:

7 days

Step-by-step explanation:

A work in 10 days

B work in 12 days

C work in 15 days

total work = LCM of 10, 12, 15

= 60

A's efficiency= 6

B's efficiency= 5

C's efficiency= 4

2days work= 15*2=30

left work= 60-30= 30

last 3 days only work C.

last 3 days work= 12

left work= 30-12= 18

18/9= 2days after B left the work..

total days to completed the work= 2+2+3=7 days