\huge \cal \underline \color{magenta}★A᭄ɴsᴡΣʀ࿐

First 2 days all three of them worked together, thus they did 2*(1/10 + 1/12 + 1/15) = 1/2 of the work.

Last 3 days only Carla worked, thus she did 3/15 = 1/5 of the work.

1 - 1/2 - 1/5 = 3/10 of the work was done by Ben and Carla:

(time)*(combined rate)=(job done)

t*(1/12 + 1/15) = 3/10

t = 2 days.

So, we have that Ben and Carla worked together for 2 days.

Total days = 2 + 3 + 2

ɴsʀ = 7

Answered by Ᏸυէէєɾϝɭყ
24

Answer:

\huge\mathtt{\red{\underline{\underline{Answer}}}}

First 2 days all three of them worked together, thus they did 2*(1/10 + 1/12 + 1/15) = 1/2 of the work.

Last 3 days only Carla worked, thus she did 3/15 = 1/5 of the work.

1 - 1/2 - 1/5 = 3/10 of the work was done by Ben and Carla:

(time)*(combined rate)=(job done)

⇢ t*(1/12 + 1/15) = 3/10

⇢t = 2 days.

So, we have that Ben and Carla worked together for 2 days.

Total days = 2 + 3 + 2

ᴀɴsᴡᴇʀ = 7