total time taken to complete the work will be
6 days
I hope it will helps u
Attachments:
Answered by
54
Firstly we will find 1 day work of both A and B, then by adding we can get collective days for them,
So,
A's 1 day work = 1/10
B's 1 day work = 1/15
(A+B)'s 1 day work = 1/10 + 1/15
= 3+2/30
= 1/6
So together they can complete work in 6 days...