A can complete a work in 12 days .A and B together can complete it in 8 days .how long will B alone take to complete the work?​

Answers

Answered by Nishitha0603
1
{Hello/:Mate}

A can do work in 12 days

A's one day work is 1/12

(A+B) 's one day work is 1/8

B alone = 1/8 - 1/12

= 1/24

= 24 days