a can complete a work in 12 days and b can complete in 8 days. a works for 8 hours every day while b works for 10 hours every day. if a and b together start working 8 hours per day in how many days will they complete the work

Answers

Answered by Anonymous
2
P can complete the work in (12 x 8) hrs = 96 hrs 

Q can complete the work in (8 x 10) hrs=80 hrs 

Therefore, P's 1 hour work=1/96   and Q's 1 hour work= 1/80

(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs  

Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11