A can complete a work in 12 days and B can complete the same work in 8 days.
What part of the work will they all together complete in 1 day?
Answers
Answered by
4
- A can complete a work in 12 days.
- B can complete the same work in 8 days.
- What part of the work will they all together complete in 1 day?
As, A can complete the work in 12 days,
Again, B can complete the work in 8 days,
Now, in 1 day, A and B together completes ,
Hope this helps you Doraemon!! ✌