Math, asked by irinelawrence4328, 11 months ago

A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --- days ?
A) 51/24
B) 87/5
C) 57/12
D) 60/11

Answers

Answered by ZiaAzhar89
8
P can complete the work in (12 x 8) hrs = 96 hrs 

Q can complete the work in (8 x 10) hrs=80 hrs 

Therefore, P's 1 hour work=1/96   and Q's 1 hour work= 1/80

(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs  

Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11

Answered by anupkumarchakra30
6

Answer:

60/11

Step-by-step explanation:

A can complete the work in 12 days working 8 hours a day

=> Number of hours A can complete the work = 12×8 = 96 hours

=> Work done by A in 1 hour = 1/96

B can complete the work in 8 days working 10 hours a day

=> Number of hours B can complete the work = 8×10 = 80 hours

=> Work done by B in 1 hour = 1/80

Work done by A and B in 1 hour = 1/96 + 1/80 = 11/480

=> A and B can complete the work in 480/11 hours

A and B works 8 hours a day

Hence total days to complete the work with A and B working together

= (480/11)/ (8) = 60/11 days

M

Please like if it is correct

Similar questions