a can complete a work in 20 days and b can complete the same work in 25 days. If both of them work together, then in 3 days what percent of the total work will be completed?
Answers
Answered by
1
A’s one day work = 1/20
B’s one day work = 1/25
A and B’s one day work = 1/20 + 1/25
5+4/20 = 9/20
Number of days = 20/9