A can complete a work in 24 days and B can complete the same work in 18 days.A & B started doing the same work together.After 4 days, A discontinued working.How many days would the work take to be completed.

Answers

Answered by rahulsihag94344
0

17 Day the work will be complete.

Answered by adnanquazi1439
0

ans will be 11 days bcz after 4 days of both work rest of work will completed by B only