Math, asked by sirajune123, 10 months ago

A can complete a work in 30 days B can do the same work in 36 days A starts working alone and after working for 5 days .A leaves the work and B carries the work forward.in how many days will B do the remaining work?

Answers

Answered by rebel23
2

Answer:

4.16 days

Step-by-step explanation:

please refer to diagram for explanation