A can complete a work in 6 days .B
can complete the same work in 8 days
How many days will be required to
Complete the work , If they work together.
Answers
Question:
A can complete a work in 6 days , B can complete the same work in 8 days. How many days will be required to complete the work , if they work together.
Answer:
24/7 days
Solution;
It is given that A can complete a work in 6 days.
Thus;
=> Time taken by A to complete a work
= 6 days
=> One day work of A = (1/6) work
Also;
It is given that B can complete a work in 8 days.
Thus;
=> Time taken by B to complete a work
= 8 days
=> One day work of B = (1/8) work
Now,
One day work of A and B together
= (1/6) work + (1/8) work
= (1/6 + 1/8) work
= { (4 + 3)/24 } work
= (7/24) work
Thus;
The time taken by A and B together
= 24/7 days.
Hence,
A and B will together complete the work in 24/7 days.
Days required to complete the work is or 3.42 (approx) days.
Given :
- A can complete a work in 6 days .
- B can complete the same work in 8 days
To find :
- Days required to complete the work if person A and person B work together.
Solution :
Person A takes 6 days to complete a piece of work.
•°• Work done by person A in one day,
---> (1)
Person B takes 8 days to complete a piece of work.
•°• Work done by person B in one day,
---> (2)
If they work together, the time taken to complain the work will be sum of person A's one day work and person B's one day work.
Adding equation (1) and (2)
+
•°• days will be required for person A and person B to complete the work if they work together.
If we convert it further into decimals then our answer :-
(approx) days.