Math, asked by cpie0059, 6 days ago

A can complete the work in 6 days and B can complete it in 8 days. If they work together how long will it take to complete the same work?​

Answers

Answered by HarshitPagadpwar
0

Step-by-step explanation:

Given,

A can do a work in = 6 days

A’s, 1 day work = 1

6

B can do a work in = 8 days

B’s, 1 day work = 1

8

Both (A+B)’s 1 day work = 1/8+1/6= 4+3 = 7

24 24

Both (A+B)’s work in = 24/7 Days

Therefore if they work together will it take 24/7 days to complete work