Math, asked by ss8366858, 6 months ago

A can complete work 4 days more than B and both together can complete a work in 4
4/5days in how many day A alone can do the work?​

Answers

Answered by smayan2015
2

Answer:

So, A alone can complete the work in 20 days.

I hope answer given help you.