A can do 1/3 of a work in 5 days and B can do 2/3 of a work in 10 days .in how many days both A and B together can do whole work:
Answers
Answered by
0
ANSWER
= 8/75
Step-by-step explanation:
A's rate is (1/3)/5
= 1/15
and B's rate is (2/5)/10
= 2/50
= 1/25.
Their combined rate is 1/15 + 1/25
= 5/75 + 3/75
= 8/75
hope this help you
Similar questions
Math,
4 months ago
Computer Science,
9 months ago
Science,
9 months ago
Social Sciences,
1 year ago
Social Sciences,
1 year ago