A can do 1/4 of a work in 5 days, while B can do 1/5 of work in 6 days. In how many days can both do it together?
Please answer me ☝️
Answers
Answered by
1
Answer:
Both "A" and "B" will together finish the work in 12 days.
Step-by-step explanation: