Math, asked by devanshmittal125, 10 days ago

A can do 1/4 of the work in 5 days, while B can do 1/5 of the work in 6 days. in how many days can both do it together​

Answers

Answered by beherap183
4

Step-by-step explanation:

A 1/4 work in 5 days

A finish total work=5×4=20days

B 1/5 work in 6 days

B finish total work=5×6=30days

A + B together finish work

=1/20+1/30

=3+2/60

=5/60

=1/12

so A+B together finish work in 12 days.