Math, asked by indushrm820, 11 months ago

A can do 2/3 of a certain work in 12 days and B Can do 1/6 of the same work in 4 days . find in how many days will they together complete the work .

Answers

Answered by ritwikVerma
0

72/7 days is the answer

Similar questions