A can do 2/3 of a certain work in 16 days and B can do 1/4 of the same work in 3days. In how many days can both finish the work, working together
Answers
Answered by
0
Step-by-step explanation:
A =2== 16
3 ==24 days to do whole work
B = 1 ==3
4 ==12 days to do whole work
take LCM for 24,12 to set the total work= 24
A= 24 days ==1 capacity/day
B= 12 days== 2 capacity/day
working together = 24 / 1+2 = 24/3
= 8 days✅